Engineers stand by dam assessment
After further inspection of the Flower
Creek Dam, the City of Libby still must replace the dam.
Core samples of the dam were taken last
fall after a visual inspection recommended further testing. The
inspection was necessary to renew the city’s operating permit with
the Montana Department of Natural Resources and Conservation.
The core samples revealed that the dam
was deteriorating. The city’s engineering firm, Morrison-Maierle,
recommended replacing the dam, in part because the dam might not
hold up to a seismic event.
As required by the DNRC, URS
Corporation conducted a peer review of Morrison-Maierle’s
analysis.
URS disagreed with the first analysis
calling the conclusion that the dam could not withstand a seismic
event premature. Structural evaluations by URS also found that the
dam, under normal loading conditions, does not appear to be
threatened at this time.
Last week Morrison-Maierle released its
response.
“We’re standing by our initial report,”
said Ryan Jones of Morrison-Maierle.
URS also recommended further testing of
the dam.
Morrison-Maierle disagreed. The
presence of extensive cracking observed along the construction
joints and through the concrete preclude a realistic expectation of
safe dam service over the long-term, the firm wrote in its
response.
“We’re not in imminent danger, but I
can’t tell you that the dam won’t fail,” Jones told the City
Council Monday.
The DNRC will not require the city to
replace the dam, Jones said, but it might not renew the city’s
permit if action isn’t taken.
Mayor Doug Roll said the dam needs
replacing.
“The dam is in tough shape,” he said.
“Our most important job is public health and safety.”
The Flower Creek Dam, built in 1946, is
located about three miles south of Libby. The dam holds back a
reservoir on Flower Creek and is the city’s sole source of
water.
Core samples taken from the dam
indicate that in some areas the dam is too weak to withstand 1,000
pounds per square inch of pressure. Typical concrete cores
demonstrate strength of 3,000-4,000 psi. A portion of the dam that
was replaced in 1966 measured over 6,000 psi. This makes it
difficult to determine the dam’s overall strength because the
concrete varies widely.
The City Council still has to decide
whether to repair or replace the dam.
Morrison-Maierle recommends replacement
because of potential cost-savings.
The firm estimates that placing a
reinforced concrete veneer on the dam would cost about $1.5
million. This would only last about 25 years, however, and dam
replacement later would be an additional $6 million. Those costs
would be combined with testing and engineering for both
reinforcement and replacement.
The City Council was scheduled to hold
a special meeting on the dam Thursday after presstime.